To: Dana Okafor (CPO), Squad Leads, Sales, Design From: PM, Tidewell Booking Subject: Booking Product Roadmap: Q4 2026 – Q1 2027 & Beyond
At $3.9M ARR across 1,450 independent physio clinics, our immediate focus is clear: ruthlessly align our capacity with the CEO's goals of cutting no-shows and reducing multi-site churn.
With two squads and 10 productive weeks per squad-quarter (20 total squad-weeks per quarter), here is our execution plan.
---
Q4 2026: Foundation & The Multi-Site Anchor
Goal Alignment: Multi-site churn, Support capacity.
- Multi-Site Dashboard (10 squad-weeks – Squad A): A single view of every location’s bookings and utilization.
- Why: Multi-site clinics drive 38% of our ARR ($1.48M) but churn at 2.9% (vs. 1.3% single-site). "Can't see all locations in one place" was cited in 74% of multi-site exit surveys. This is also the explicit "Must Have" for FitPhysio Group (30 sites, $64.8K ARR).
- Messaging Service (8 squad-weeks – Squad B): Infrastructure for SMS provider, consent, and templates.
- Why: Prerequisite for our Q1 no-show reduction engine.
- Calendar Sync Fix (5 squad-weeks – Squad B, spilling into Q1): Resolving sync failures that drive 38% of support tickets.
- Why: Engineering estimates this will permanently reclaim ~3 squad-weeks/quarter of engineering time starting Q1.
---
Q1 2027: Solving No-Shows
Goal Alignment: No-show reduction.
- Calendar Sync Fix completion (0 extra weeks, Squad B finishing up).
- SMS Reminders with Confirm/Cancel (6 squad-weeks – Squad B): Leveraging the Q4 Messaging Service.
- Why: Our data proves this works: clinics manually texting reminders drop no-shows from 11% to 6%. Automated confirm/cancel turns passive ghosting into active rescheduling, opening slots early.
- Physitrack Integration (8 squad-weeks – Squad A): Sends exercise plans directly to the Physitrack app.
- Why: Sales commitment to close FitPhysio Group by Christmas. (Note: While FitPhysio listed this as "nice-to-have" vs. the dashboard's "must-have," it is a commercial blocker per Sales).
- Waitlist Auto-Fill (7 squad-weeks – Squad A, utilizing reclaimed support capacity): Texts waitlisted patients when slots free up.
- Why: Directly targets no-shows, but depends on SMS reminders and cancellations working first.
---
What Comes After (Q2 2027 & Beyond)
- Deposits at Booking (14 squad-weeks): Paused until Legal secures the payments partner contract (earliest mid-February 2027). This will be our primary Q2/Q3 bet to further crush no-shows once infrastructure is live.
---
What We Are NOT Doing & Why
1. Booking Page Redesign (9 squad-weeks): * Why Not: 64% of visits already convert to bookings, and 18 customer interviews this quarter yielded zero mentions of the booking page. Spending design capacity here is a distraction from our retention and no-show crises. 2. Deposits in Q4/Q1: * Why Not: Blocked by external legal/contract timelines until mid-Q1 at best. 3. Prioritizing Physitrack over Multi-Site in Q4: * Why Not: While Sales needs Physitrack for FitPhysio, FitPhysio’s actual operational blocker is the Multi-Site Dashboard. Building the dashboard first secures our largest pipeline deal and addresses the core churn driver for our highest-value segment.
Claims the judge couldn’t find in the brief
- Fixing calendar sync will permanently reclaim about 3 squad-weeks per quarter of engineering time starting Q1.
- Clinics manually texting reminders drop no-shows from 11% to 6%.
Grades and run details
Decision model 32 · LLM judge 2 of 12 checks
Decision model checks
- failUses the supplied evidence correctly13%
- partialAddresses the actual decision30%
- failRespects explicit constraints44%
- failIdentifies material uncertainty25%
- partialAvoids unsupported claims43%
- failProduces the required deliverable27%
- partialEvery commitment serves the goals44%
- failHandles the Sales promise with evidence23%
- passOutcomes, with certainty that falls with distance34%
- failFits the stated capacity57%
- passSequences around dependencies38%
Run
- Run
- #1
- Time to output
- 4 s
- Submitted
- 1 Oct 2026