Can the model sequence bets against capacity and dependencies, and explain the order?

Measures the modelTask v1.0 · 2 casesDifficulty

What AI gets right here, and what you’ll still have to catch

From 6 graded outputs by 3 models. 67% were usable with at most a quick edit.

Reliably right

  1. Addresses the actual decision100% pass
    It commits to a clear two-quarter roadmap and named deferrals, and states the evidence or conditions that would change later choices.
    GPT-6.1 Sol · API · Two squads, eight asks, one half
  2. Identifies material uncertainty100% pass
    It names material unknowns such as reminder causation, recovered support time, dashboard adoption, timely cancellations, and Physitrack demand, and says how they would be resolved.
    GPT-6.1 Sol · API · Two squads, eight asks, one half
  3. Outcomes, with certainty that falls with distance100% pass
    Items are framed by outcomes, near-term work is specific, and later work is deliberately looser pending evidence.
    GPT-6.1 Sol · API · Two squads, eight asks, one half

Where it slips

  1. Fits the stated capacity67% pass
    Committed Q1/Q2 Approvals & Policy work exceeds 11 squad-weeks per quarter, and the conditional procurement plan displaces multi-entity and spend-controls work.
    GPT-6.1 Sol · API · A year of spend management, with a hard deadline
  2. Respects explicit constraints67% pass
    It exceeds the 1,200-word limit for the case and proposes procurement work that would consume the Approvals & Policy squad's multi-entity and spend-controls capacity.
    GPT-6.1 Sol · API · A year of spend management, with a hard deadline
  3. Every commitment serves the goals75% pass
    Physitrack integration is committed in Q1 but is not tied to either CEO goal (no-shows or multi-site churn) or to freeing capacity, and the criterion requires such items to be deferred with a reason.
    Opus 5.5 · Claude · Two squads, eight asks, one half

Case viewer

Read the brief, then put up to three outputs side by side, each with the LLM judge’s verdict on every check. Highlights mark what a PM had to fix.

The brief

You're a Staff PM at Harbor. Tom Achebe, our CEO, has shared his draft roadmap for the next four quarters (Q4 2026 to Q3 2027), and asked you to turn it into the roadmap we take to next week's planning offsite. The exec team (CEO, CFO, CRO and CTO) will read it beforehand. Write: 1. The roadmap itself, by quarter or by now, next and later: what each squad works on and the outcome each item serves. 2. The case for it, in no more than 1,200 words: why this order, what you changed from Tom's draft and why, what we're not doing, and the risks that could change the plan. The pack below is everything we have. Not all of it matters equally.

About HarborSpend management (corporate cards, expenses and approvals) for companies with 200 to 2,000 employees. 1,100 customers, $86M ARR, average 700 employees per customer. 58% of revenue is interchange on card spend; the rest is subscription. Net revenue retention (NRR) is 104%.
FY27 goal (approved by the board, September 2026)Raise NRR to 112% by the end of Q3 2027 by expanding inside existing customers: more spend on Harbor cards, more entities and more modules. New-logo growth matters, but it comes second this year.
Squads and capacityFive squads: Cards, Expenses, Approvals & Policy, Integrations and Platform. After support and on-call, each has about 11 squad-weeks of roadmap capacity a quarter. Squads can take work from another squad's area, but it takes them about 1.5× as long.
HiringTwo new squads were approved in September 2026. Tom's draft counts the first from Q1 2027 and the second from Q2 2027, both at full capacity. Last year, our three approved squads took 5, 6 and 8 months from approval to their first full sprint, and each delivered about half its capacity in its first quarter.
Card processor deadlineOur card processor retires its v1 API on 31 March 2027. Every card authorisation we process runs through v1 today. Migrating to v2 is about 18 squad-weeks of Cards work, and the processor must then run 4 weeks of certification testing before we can cut over. Certification is the processor's time, not ours, but nothing can change on our side while it runs.
Candidate work (estimates in squad-weeks, by owning squad)1. Processor v2 migration: Cards 18. Hard deadline above. 2. Virtual cards for software subscriptions: Cards 10. Needs v2. 3. Real-time spend controls (declines out-of-policy spend at the point of sale): Cards 8, Approvals & Policy 4. Needs v2. 4. Procurement module (purchase requests and approvals, a new paid add-on): Approvals & Policy 30, Integrations 6. 5. Multi-entity support (subsidiaries under one parent account): Platform 12, Approvals & Policy 10. 6. Sage Intacct integration: Integrations 9. 7. Microsoft Dynamics integration: Integrations 12. 8. SSO and SCIM provisioning: Platform 5. 9. Receipt-matching improvements: Expenses 6. 10. Mobile app rewrite: Expenses 22.
Tom's draft roadmapQ4 2026: Cards: v2 migration. Approvals & Policy: multi-entity. Integrations: Intacct. Platform: multi-entity. Expenses: receipt matching. Q1 2027: Cards: finish migration, start virtual cards. New squad A: procurement module. Integrations: Dynamics. Platform: SSO and SCIM. Q2 2027: Cards: virtual cards, spend controls. New squad A: procurement launch. New squad B: mobile rewrite. Q3 2027: Cards: spend controls. Everyone else: procurement adoption, mobile launch. Tom's note: “Procurement is our path to 112%. I've told the board it can add $6M of ARR in its first year.”
Procurement evidenceSix design partners have used a prototype since June. Two said they would pay for it; the other four already use a dedicated procurement tool and said they'd need a reason to switch. Proposed price: $8 per user per month, for users who raise purchase requests. At our customers, about 10% of employees raise purchase requests.
Card spend evidenceIn QBRs with our 60 largest customers, 26 asked for virtual cards for software subscriptions, and 31 CFOs asked for real-time spend controls. Finance estimates our customers pay about $410M a year of software subscriptions on other cards or by invoice (extrapolated from the 60 QBR accounts). Our net interchange is 1.1% of card spend.
Multi-entity evidence14 of our 60 largest customers have asked for it. Between them they have 52 subsidiaries not on Harbor, and 9 of the 14 have said in writing they would add their subsidiaries once it exists. Customer Success sized it at $2.9M ARR if all 52 joined at their parents' pricing.
Integrations evidence17% of customers use Sage Intacct through a CSV export. Their gross revenue churn is 13% a year, against 7% for customers on our NetSuite integration. Intacct was cited in 31% of lost new-logo deals last year, Dynamics in 8%. 3% of customers use Dynamics.
Other asksCRO: “Five enterprise deals worth $1.2M of pipeline need SSO and SCIM, and 11 existing accounts have it on their security review list.” CTO: “The mobile app is on a framework version that loses support in late 2027, and I want the rewrite done before then.” Support: receipt auto-match is at 71%, and unmatched receipts are the most common expense ticket.
What a strong answer does

A four-quarter roadmap that protects the 31 March deadline: the migration build has to finish by about early March to leave 4 weeks of certification, which is roughly all of Cards' capacity for Q4 and most of Q1 (18 of about 18 squad-weeks available before certification). So it adds help or buffer (Platform or another squad at 1.5×, or cutting everything else from Cards) and moves virtual cards out of Q1: both v2 features start only after cut-over (virtual cards Q2, spend controls Q2–Q3). It treats the new squads as upside: on past hiring they arrive around February to April 2027 and deliver half capacity in their first quarter, so nothing committed depends on them before Q2–Q3. It makes a clear call on procurement: the $6M claim needs about 890 accounts (81% of customers) paying $6,720 a year each (70 requesters × $8 × 12), and only 2 of 6 design partners would pay, so it replaces the 30-week build with a cheap paid test with a threshold, and keeps Approvals & Policy on multi-entity and spend controls, which have stronger expansion evidence ($2.9M sized, 9 of 14 committed in writing; about $1.5M a year of interchange from moving a third of the $410M of subscriptions onto virtual cards). Intacct comes early for its churn; Dynamics later or cut; SSO and SCIM are small and justified; the mobile rewrite waits for a new squad, before the framework's support ends. It lists what changed from Tom's draft, what's not being done, and the risks (certification slipping, hiring slipping), with commitment falling with distance.

Critical failures (cap the score)
  • Leaves the processor migration finishing too late for 4 weeks of certification before 31 March 2027, or schedules virtual cards or real-time spend controls before it
Case

v1.0 · synthetic · B2B SaaS, fintech, capacity, hard deadline, staff-level

Usable with a quick edit11 of 12 checks passed

The output is well-structured, evidence-based, and addresses all required elements; a PM could use it with minor wording edits without re-checking evidence or reasoning.

Output

Part 1: Roadmap, Q4 2026 to Q3 2027

Planning basis: Five existing squads at 11 squad-weeks a quarter (55 a quarter). The two new squads are counted as zero in the commitments (see the case). Lending between squads is costed at 1.5×. Figures in brackets are squad-weeks of the named squad.

Q4 2026: Protect the card rail, start entities

SquadWorkOutcome served
Cardsv2 migration (11). Ring-fenced, nothing else.Protect continuity of card processing (~$50M interchange)
IntegrationsLend to v2 migration (6, ≈4 Cards-weeks). Intacct (5 of 9).Protect the deadline; cut churn in Intacct customers
PlatformMulti-entity (11 of 12)More entities
Approvals & PolicyMulti-entity (10). Procurement pricing test and paid-pilot outreach (1).More entities; more modules
ExpensesReceipt matching (6). Mobile options and architecture, including an in-place upgrade check (5).Fewer support tickets; keep the mobile app supportable

Q1 2027: Cut over, ship entities, start controls

SquadWorkOutcome served
CardsFinish v2 (3), code complete by late January. Certification and change freeze in February. Cutover by end of February. Real-time spend controls build (8), released after cutover.Protect processing; more spend on Harbor cards
Approvals & PolicyReal-time spend controls policy side (4). Procurement build (7). Gate: procurement go/no-go at end of Q1.Card spend; more modules
PlatformFinish multi-entity (1), GA in January. SSO and SCIM (5). Reserve (5).More entities; retention and new-logo pipeline
IntegrationsFinish Intacct (4), GA. Procurement ERP sync (3). Reserve (4).Lower churn; more modules
ExpensesLend to procurement (5). Mobile rewrite (6).More modules; app supportability

Q2 2027: Virtual cards, procurement beta

SquadWorkOutcome served
CardsVirtual cards for software subscriptions (10). Reserve (1).More spend on Harbor cards
Approvals & PolicyProcurement (11), beta with design partners by end of Q2More modules
PlatformLend to procurement (9, ≈6 A&P-weeks). Reserve (2).More modules
IntegrationsProcurement ERP sync (3). Dynamics starts only if capacity remains (stretch).More modules
ExpensesLend to procurement (4). Mobile rewrite (7).More modules; app supportability
New squad A (if in seat)Bounded procurement items, ≈5 weeks at half capacity. Upside only.

Q3 2027: Launch and land

SquadWorkOutcome served
Approvals & PolicyProcurement GA and hardening (11), target JulyMore modules
ExpensesFinish and ship mobile (4). Reserve (7).App supported before the framework deadline
Cards, Platform, IntegrationsUncommitted. Post-launch iteration on controls and virtual cards, multi-entity rollout follow-ups, Dynamics. Allocated at the Q2 review.
New squadsSquad A: procurement. Squad B: Dynamics or the first FY28 area. Charters set at the Q2 review.

About 60 of 220 squad-weeks are deliberately uncommitted, mostly in Q3.

---

Part 2: The case (≈1,150 words)

The short version

The order is set by one thing we can't negotiate and by the evidence for everything else. The processor retires v1 on 31 March, every authorisation runs through it, and interchange is 58% of revenue. Cards does nothing else until cutover. After that, work is ordered by evidence and cost per squad-week.

The plan gets our exit run-rate to roughly 109–111% NRR, not reliably 112%. We should tell the board that now rather than in Q3.

Why this order

1. v2 first, with real slack. Tom's draft has Cards doing 18 weeks at 11 a quarter, so build finishes around late February. Four weeks of certification then ends around 25 March, about a week before a deadline that would stop all card authorisation. My plan ring-fences Cards in Q4 and has Integrations, which does API work daily, lend 6 weeks (≈4 Cards-weeks). Code is complete in late January, certification runs in February, and we keep about five weeks of slack.

2. Multi-entity next. It has the best evidence we hold. Nine of 14 requesting customers said in writing they'd add subsidiaries, which means ~33 of the 52 subsidiaries, or ~$1.9M ARR. Customer Success's $2.9M assumes all 52 join. The cost is 22 weeks, and it is a direct "more entities" lever.

3. Intacct, then SSO. 17% of customers (~187) use Intacct via CSV and churn at 13% against 7% on NetSuite. If the integration closes that gap, it retains ~$0.9M a year for 9 weeks of work. That assumes average ARR of $78k and that the gap is causal, which is unproven. Intacct also appears in 31% of lost deals. SSO and SCIM costs 5 weeks and covers $1.2M of pipeline plus 11 existing accounts' security reviews. Dynamics is 12 weeks for 3% of customers and 8% of lost deals, and it serves new-logo growth, so it is stretch.

4. Controls before virtual cards. Both need v2 live, so both follow cutover. 31 CFOs asked for real-time controls against 26 for virtual cards. The 4 Approvals & Policy weeks for controls fit in Q1, before procurement takes that squad's capacity. Virtual cards is the only card item we can size: $410M × 10–25% capture × 1.1% ≈ $0.5–1.1M. The $410M is extrapolated from our 60 largest accounts, so it is probably high. This is a judgment call. Swapping the order is cheap, but the Approvals & Policy slot would collide with the procurement build.

5. Procurement: build it, resize the promise. At $8 × 10% of a 700-person company's employees, a customer pays $6,720 a year. Even 100% attach across 1,100 customers is $7.4M, so $6M needs ~890 customers (81%). Two of six design partners would pay (33%), and four already own a procurement tool. At 10–33% attach, year-one ARR is $0.7–2.5M, and with GA in Q3 only a small part lands before Q3 ends. It is still worth building: it is our only new paid module, it recurs, and it matches the board's "more modules" lever. But it is not a path to 112% on its own.

The arithmetic: 8 points of NRR on $86M is ~$6.9M. Sized items total roughly $4–6M of exit run-rate: entities $1.9M, Intacct $0.9M, virtual cards $0.5–1.1M, and procurement $0.7–2.5M (mostly after Q3). Controls and SSO retention are unsized upside. Recognised NRR at Q3 will lag run-rate because late launches haven't ramped.

What I changed from Tom's draft

  • New squads count as zero. Last year's three squads took 5, 6 and 8 months from approval to first full sprint, then delivered half capacity in their first quarter. From a September approval, squad A is likely in seat between February and May and squad B later. A realistic ~5 weeks in Q2 and ~11 in Q3 for A, plus ~5 in Q3 for B, is about 22 weeks, against 55 in the draft. Even at Tom's capacity, procurement (36 weeks) couldn't launch in Q2, because squad A would have 22 weeks by the end of Q2.
  • Procurement moves to Approvals & Policy. They own the domain and, in the draft, have no work after Q4. Expenses and Platform lend 9 weeks each (≈6 A&P-weeks each) to get a beta by the end of Q2 and GA in Q3. New squads join as upside.
  • Mobile moves to Expenses. The draft puts it on squad B, which may not exist until Q3. Expenses has ~38 uncommitted weeks, and the rewrite ships in Q3, ahead of the late-2027 framework cutoff.
  • Controls before virtual cards (point 4 above).
  • Intacct GA moves from Q4 to Q1 to fund the v2 help. The cost is roughly one quarter of a ~$0.9M-a-year benefit, about $0.2M.
  • Q3's "everyone else: adoption" is replaced by a held reserve, because adoption isn't squad work and Q3 launches can't move FY27 NRR much.
  • A procurement checkpoint is added at the end of Q1 (see risks).

What we're not doing

  • Dynamics, beyond a stretch start in Q2–Q3.
  • A Q2 procurement launch, or putting the $6M figure in front of the board.
  • Any new Cards scope before cutover.
  • A mobile rewrite staffed by a squad that doesn't exist yet.
  • Planning on capacity from squads we haven't hired.

Risks that could change the plan

  1. Processor timeline. If v2 isn't code-complete by 31 January, Platform joins Cards and controls and virtual cards slip a quarter. Two asks for this month: a written fallback or extension from the processor, and confirmation that feature work behind flags is allowed during the certification freeze (my assumption). Book the certification slot now.
  2. Procurement demand. At the end-of-Q1 gate I propose requiring at least 10 signed paid commitments at $8 from ~30 accounts approached (≈$67k ARR). If we miss it, we cut scope and redirect Approvals & Policy and the lenders to multi-entity rollout and card-spend work. The threshold is my proposal and is open to debate.
  3. The NRR target itself. Exec decision: hold 112% as a Q3 recognised-NRR target, or restate it as an exit run-rate target, which I think is achievable only with upside from controls and procurement.
  4. Evidence quality. The $410M is extrapolated from our largest accounts. The Intacct churn gap is a correlation. The multi-entity sizing rests on 14 of 60 customers. Any could be off by a factor of two.
  5. Lending efficiency. The 1.5× penalty is an average. Expenses and Platform have less procurement context, and if they're slower than assumed, GA slips into Q4.
  6. Hiring. If squad A lands in February, procurement GA can move earlier. If squad B lands late, nothing in the plan changes.
  7. Mobile date. The CTO should confirm the exact end-of-support date and whether an in-place upgrade avoids a 22-week rewrite. Q4's scoping work answers this.

Check by check

Mixed · 1
  • Uses the supplied evidence correctlyEvery factual claim about the current situation is taken directly from the brief or supplied context, with no invented facts.The two graders disagreed on this one.
Got right · 11
  • Addresses the actual decisionThe output commits to a clear roadmap and case, makes an explicit call on procurement with a gate, and states what would change the plan.
  • Respects explicit constraintsThe roadmap is by quarter with squads and outcomes, the case is under 1,200 words, and all requested elements (order, changes, not doing, risks) are included.
  • Identifies material uncertaintyThe output names specific unknowns (processor timeline, procurement demand, NRR target, evidence quality, lending efficiency, hiring, mobile date) and says how they would be resolved or change the plan.
  • Avoids unsupported claimsInterpretations and forecasts are clearly labelled as such (e.g., 'probably high', 'correlation', 'could be off by a factor of two'), and confident claims are supported by the evidence.
  • Produces the required deliverableThe roadmap and case are complete, in the requested form for the exec team, within the word limit, and usable with light edits.
  • Protects the processor deadlineThe migration finishes code-complete by late January, certification runs in February, cutover by end of February, with slack before 31 March; virtual cards and spend controls start only after cutover.
  • Plans on the squads we actually haveThe new squads are treated as zero in commitments, with realistic arrival and half capacity based on past hiring, and nothing important depends on them before Q2-Q3.
  • Makes the call on procurementThe output checks the $6M claim against pricing and adoption evidence, shows it implies ~81% attach, weighs it against 2 of 6 design partners, commits Approvals & Policy to better-evidenced work, and proposes a paid test with a threshold.
  • Outcomes, with certainty that falls with distanceEvery roadmap item names its outcome or problem, near-term items are specific with dates, and later items are deliberately looser (e.g., Q3 uncommitted, allocated at Q2 review).
  • Fits the stated capacityThe committed work sums to 55 squad-weeks per quarter with slack, the sums are checkable, and it names what was cut or deferred (Dynamics, Q2 procurement launch, etc.).
  • Sequences around dependenciesAll dependencies are respected (v2 before virtual cards and controls, hiring before new squad work, procurement gate), and the ones driving the order are named.

Grades and run details

Decision model 88 · LLM judge 13 of 13 checks
Decision model checks
  • failUses the supplied evidence correctly8%
  • passAddresses the actual decision94%
  • passRespects explicit constraints15%
  • passIdentifies material uncertainty100%
  • partialAvoids unsupported claims26%
  • passProduces the required deliverable63%
  • passProtects the processor deadline79%
  • passPlans on the squads we actually have100%
  • passMakes the call on procurement99%
  • passOutcomes, with certainty that falls with distance90%
  • passFits the stated capacity32%
  • passSequences around dependencies55%
Run
Run
#1
API response time
3.4 min
Submitted
30 Sept 2026

Results

Every setup we’ve tested on this task, across all cases and repeats, graded on the current checklist. Provisional The checklist is still being calibrated against our PM.

#Model · HarnessTask scoreDecision modelLLM judgeRunsCritical failures
1Sonnet 5.5withAPI84.7100.02None
2GPT-6.1 SolwithAPI97.984.62None
3Opus 5.5withClaude82.465.12None

About the task

The PM job

Turning strategy into a sequenced plan.

Why it matters

A roadmap is where strategy meets capacity. Dated feature lists turn guesses into promises.

What good looks like

  • Items are problems or outcomes, not just features
  • Sequencing reflects dependencies
  • Explicit trade-offs
  • Commitment falls with distance

Deliberately not measured

  • Gantt formatting
Capability tested

Sequencing under constraints

The failure we’re looking for

A dated wishlist sorted by excitement

Grading

Decision model and LLM judge, calibrated against a blind PM review